ROUTE 47 ENTERS STAGE 1A ON NOVEMBER 2, 2026:
Major Traffic Changes and McConnell Road Closure Through Mid-2027
McConnell Road will close between Route 47 and Zimmerman Road beginning Monday, November 2, with the closure expected through mid-2027. Detours will use Country Club and Zimmerman roads. Route 47 will remain open with one lane in each direction, with additional restrictions affecting Judd Street, Irving Avenue and eastbound Route 120. Visit the Construction Updates Page for all detour information!
Please allow extra travel time and continue supporting Woodstock businesses. Thank you for your patience as these long-term improvements move forward!
Please allow extra travel time and continue supporting Woodstock businesses. Thank you for your patience as these long-term improvements move forward!
A CRITICAL INVESTMENT IN WOODSTOCK
|
The City of Woodstock is partnering with the Illinois Department of Transportation (IDOT) on the Route 47 Widening Project, to promote and support a high quality of life for its community. Through these improvements, this project seeks to honor the City's mission of creating a safe environment, fostering opportunities, supporting growth, and celebrating Woodstock’s heritage and culture.
Construction began in early April with water main removal and replacement. These upgrades will improve water service for both residential and commercial properties in the area. The project limits are 2.25 miles of Illinois Route 47 (Route 47) from Illinois Route 120 (IL 120) to US Route 14 (US 14), expanding the road to have two lanes in each direction. The limits of construction are Davis Road at the south end to Grove Street at the north end. Roundabouts will also be constructed where Route 47 intersects with Lake Avenue, McConnell Road, and Judd Street/Irving Avenue to improve safety and traffic flow. This significant expansion, combined with the installation of an underground drainage system throughout the roadway section, will restore and upgrade the aging infrastructure. |
Additionally, sidewalk improvements will be constructed on the western side of Route 47, and a shared use path will be installed on the eastern side of Route 47, both spanning from Grove Street to Davis Road. This will further enhance connectivity throughout the corridor for pedestrians, creating a safe space for users as they visit one of our many businesses on Route 47.
IDOT is currently anticipating that road construction will take approximately 2.5 years with completion of the project anticipated by the end of 2028.
IDOT is currently anticipating that road construction will take approximately 2.5 years with completion of the project anticipated by the end of 2028.